estimation-agent

star 0

Produces detailed Cost Estimation and Man Hours breakdown for software projects. Use this skill whenever the user wants to: estimate development cost, calculate man-hours per feature or sprint, produce a project budget, compare team configurations, create cost proposals for clients, or get ROI analysis. Triggers on: "ประเมิน cost", "คำนวณ man hours", "งบประมาณโปรเจกต์", "ค่าใช้จ่ายพัฒนา", "ราคาโปรเจกต์", "estimate", "how much will this cost", "how long will this take", "project budget", "cost breakdown", "resource planning", "เตรียม proposal ราคา". ALWAYS use this skill — not just xlsx/docx alone — when the goal is a complete, justified cost and timeline estimate for a software project.

ThanabordeeN By ThanabordeeN schedule Updated 3/11/2026

name: estimation-agent description: > Produces detailed Cost Estimation and Man Hours breakdown for software projects. Use this skill whenever the user wants to: estimate development cost, calculate man-hours per feature or sprint, produce a project budget, compare team configurations, create cost proposals for clients, or get ROI analysis. Triggers on: "ประเมิน cost", "คำนวณ man hours", "งบประมาณโปรเจกต์", "ค่าใช้จ่ายพัฒนา", "ราคาโปรเจกต์", "estimate", "how much will this cost", "how long will this take", "project budget", "cost breakdown", "resource planning", "เตรียม proposal ราคา". ALWAYS use this skill — not just xlsx/docx alone — when the goal is a complete, justified cost and timeline estimate for a software project.

Estimation Agent

รับ Backlog / Sprint Plan แล้วผลิต Cost & Man Hours Package ครบชุด ใช้เป็น Input สำหรับ Proposal ลูกค้า หรือวางแผน Resource ภายใน


Deliverables

# ไฟล์ Skill เนื้อหา
1 manhours-breakdown.xlsx xlsx Hours ทุก Task แยกตาม Role / Sprint / Feature
2 cost-estimation.xlsx xlsx ต้นทุน Dev + Infra + Buffer + สรุปรวม
3 project-proposal.docx docx เอกสาร Proposal พร้อมส่งลูกค้าหรือ Management

Input ที่รับได้

  • sprint-plan.xlsx จาก product-backlog-agent ← แม่นยำที่สุด
  • product-backlog.xlsx จาก product-backlog-agent ← ประมาณจาก Story Points
  • ข้อความบรรยาย Features ← rough estimate เท่านั้น

ถ้าไม่มี sprint-plan ให้แจ้ง User และเสนอให้รัน product-backlog-agent ก่อน หรือถามขนาดโปรเจกต์และทำ rough estimate แทน


Step-by-Step Workflow


Step 0 — รับ Input และตั้งค่า Rate Card

ก่อนคำนวณ ถามผู้ใช้ (หรือใช้ค่า Default):

ถามเป็นกลุ่มเดียว:

1. อัตราค่าจ้าง Dev แต่ละ Role (ถ้าไม่มีใช้ค่า default)
2. จำนวน Dev แต่ละ Role ในทีม
3. ต้องการ 3 Scenarios ไหม? (Optimistic / Realistic / Pessimistic)
4. รวม Infrastructure Cost ด้วยไหม?
5. รูปแบบการคิดราคา: Internal Cost หรือ Client Proposal (+ Margin)?

อ่าน references/rate-card.md สำหรับค่า Default Rate ตามตลาดไทย


Step 1 — Man Hours Breakdown (xlsx)

อ่าน /mnt/skills/public/xlsx/SKILL.md ก่อนสร้าง

สร้าง manhours-breakdown.xlsx ด้วย Structure ดังนี้:

Sheet 1: Hours by Task

Column เนื้อหา
Sprint Sprint 1, 2, ...
Story ID อ้างอิงจาก Backlog
Story Name ชื่อ User Story
Task ID TSK-001
Task Name ชื่องาน
Type Frontend / Backend / DB / DevOps / Design / QA
Assignee Role หรือชื่อ
Estimate (hrs) ชั่วโมงประเมิน
Optimistic (hrs) -20%
Pessimistic (hrs) +40%
Notes ความเสี่ยง / สมมติฐาน

Sheet 2: Summary by Role

Role Total Tasks Optimistic hrs Realistic hrs Pessimistic hrs
Frontend Dev X X X X
Backend Dev X X X X
DB/DevOps X X X X
QA X X X X
Total

Sheet 3: Summary by Sprint

Sprint Goal Start End Total hrs FE hrs BE hrs QA hrs

Sheet 4: Summary by Epic/Feature

Epic Feature Stories Total hrs % of Project

Apply:

  • Conditional formatting: สีแดงถ้า Task > 16 hrs (ควรแตกย่อย)
  • Chart: Pie chart แสดง % hours by Role
  • Chart: Bar chart แสดง Hours per Sprint

Step 2 — Cost Estimation (xlsx)

อ่าน /mnt/skills/public/xlsx/SKILL.md ก่อนสร้าง

สร้าง cost-estimation.xlsx ด้วย Structure ดังนี้:

Sheet 1: Rate Card

Role Headcount Daily Rate (THB) Hrs/Day Hourly Rate
Senior Frontend Dev X X 8 =Daily/8
Senior Backend Dev X X 8 =Daily/8
Junior Dev X X 8 =Daily/8
QA Engineer X X 8 =Daily/8
DevOps / Infra X X 8 =Daily/8
Project Manager X X 8 =Daily/8

ทุก Rate ต้องอ้างอิงจาก references/rate-card.md ใส่เป็น Input cells (สีฟ้า) เพื่อให้ User แก้ไขได้

Sheet 2: Development Cost

Category Role Hours Rate/hr Cost (THB)
Sprint 1 Frontend X X =Hours*Rate
Sprint 1 Backend X X
...
Subtotal Dev
+ Buffer (20%)
Total Dev Cost

Sheet 3: Infrastructure Cost

Item Type Unit Qty/Month Cost/Unit Monthly 12 Months
Cloud Server AWS EC2 / GCP Instance 2 X
Database RDS / Cloud SQL Instance 1 X
Storage S3 / GCS GB 100 X
CDN CloudFront GB Transfer 50 X
Domain + SSL - Year 1 X
Monitoring Datadog/Sentry Month 12 X
Total Infra (Year 1)

อ่าน references/infra-cost.md สำหรับ Pricing Reference

Sheet 4: Total Project Cost Summary

┌─────────────────────────────────────────────────────┐
│              PROJECT COST SUMMARY                    │
├──────────────────────────┬──────────────────────────┤
│                          │  Optimistic │  Realistic  │  Pessimistic
├──────────────────────────┼─────────────────────────┤
│ Development Cost         │             │             │
│ + QA & Testing           │             │             │
│ + Infrastructure (Y1)    │             │             │
│ + Contingency Buffer     │             │             │
├──────────────────────────┼─────────────────────────┤
│ TOTAL PROJECT COST       │             │             │
├──────────────────────────┼─────────────────────────┤
│ Timeline (weeks)         │             │             │
│ Team Size                │             │             │
│ Cost per Sprint          │             │             │
└──────────────────────────┴─────────────────────────┘

Sheet 5: Client Proposal Price (ถ้าเป็น Outsource)

Item Cost Margin % Selling Price
Development 30%
Infrastructure Setup 20%
Project Management 30%
Total Proposal Price

Step 3 — Project Proposal Document (docx)

อ่าน /mnt/skills/public/docx/SKILL.md ก่อนสร้าง

สร้าง project-proposal.docx — เอกสารส่งลูกค้าหรือ Management

โครงสร้าง:

[หน้าปก]
โครงการ: [ชื่อ]
เตรียมโดย: [ทีม]
วันที่: [วันที่]
เวอร์ชัน: 1.0

1. Executive Summary (1 หน้า)
   - โปรเจกต์นี้คืออะไร ทำไมต้องทำ
   - ผลลัพธ์ที่คาดหวัง
   - ต้นทุนและระยะเวลาโดยสรุป

2. Scope of Work
   - สิ่งที่รวมอยู่ในราคานี้
   - สิ่งที่ไม่รวม (Out of Scope)
   - Assumptions

3. Timeline & Milestones
   Sprint-by-Sprint Roadmap พร้อม Deliverable แต่ละ Sprint

4. Team Structure
   Role / จำนวน / ความรับผิดชอบ

5. Cost Breakdown
   ตารางสรุป 3 Scenarios
   (ดึงมาจาก cost-estimation.xlsx Sheet 4)

6. Payment Terms (ถ้าเป็น Client Proposal)
   - งวดที่ 1: X% เมื่อ Sign Contract
   - งวดที่ 2: X% เมื่อ UAT ผ่าน
   - งวดที่ 3: X% เมื่อ Go Live

7. Risks & Mitigation
   | Risk | Probability | Impact | Plan |

8. Terms & Conditions (ถ้าจำเป็น)

Step 4 — Deliver + Summary

✅ Estimation Package พร้อมแล้ว

⏱️ manhours-breakdown.xlsx
   Realistic:    XXX hrs  (~XX สัปดาห์)
   Optimistic:   XXX hrs  (~XX สัปดาห์)
   Pessimistic:  XXX hrs  (~XX สัปดาห์)

💰 cost-estimation.xlsx
   Development:  ฿XXX,XXX
   Infrastructure: ฿XX,XXX/ปี
   Total (Realistic): ฿XXX,XXX

📄 project-proposal.docx
   พร้อมส่ง Management / ลูกค้า

Estimation Rules

อ่าน references/estimation-rules.md สำหรับกฎการประมาณเวลาและ Buffer ที่ควรใช้


Handling Special Cases

ไม่มี Sprint Plan: → ใช้ Story Points จาก Backlog × Velocity Rate จาก references/estimation-rules.md

ต้องการเฉพาะ Rough Estimate: → ทำแค่ Sheet Summary ของ cost-estimation.xlsx ไม่ต้องแตก Task

โปรเจกต์เป็น Outsource / Client Proposal: → เพิ่ม Margin Sheet และ Payment Schedule ใน cost-estimation.xlsx

ผู้ใช้มี Rate Card ของตัวเอง: → ใช้ Rate ที่รับมา แทนค่า Default ใน rate-card.md


Reference Files

  • references/rate-card.md — อัตราตลาด Dev ไทยแยกตาม Seniority และ Role
  • references/infra-cost.md — ราคา Cloud / Infrastructure Reference
  • references/estimation-rules.md — กฎ Buffer, Velocity, และวิธีคำนวณ
Install via CLI
npx skills add https://github.com/ThanabordeeN/gemini-productivity-skills --skill estimation-agent
Repository Details
star Stars 0
call_split Forks 0
navigation Branch main
article Path SKILL.md