Use this skill after generating a daily report to review it for completeness, consistency, and accuracy against project intelligence. Catches missing inspections, unrecognized subs, weather threshold conflicts, and other gaps before the report is finalized.

mgoodman60 By mgoodman60 schedule Updated 2/25/2026

name: report-qa description: > Use this skill after generating a daily report to review it for completeness, consistency, and accuracy against project intelligence. Catches missing inspections, unrecognized subs, weather threshold conflicts, and other gaps before the report is finalized. version: 1.0.0

Report QA

Overview

Review a generated daily report against project intelligence to catch gaps, inconsistencies, and missing information before the report is finalized. This skill runs automatically after report generation as a quality check.

When to Run

This skill is triggered after the daily-report-format skill generates the report content but before the final .docx is created. It reviews the structured report data and flags issues that should be addressed.

QA Mode Selection

This skill operates in one of two modes, determined by the calling command:

Mode Triggered By Checks Run Output Prefix
Daily /daily-report command, /amend-report command Checks 1–10 below "Report QA Complete"
Weekly /weekly-report command Checks W1–W6 below "Weekly Report QA Complete"

The calling command determines the mode. When called from /daily-report or /amend-report, run ONLY the daily checks (1–10). When called from /weekly-report, run ONLY the weekly checks (W1–W6). Never run both sets on the same report.

Amended reports: When called from /amend-report, run daily QA checks ONLY on the sections that were modified. Present results with the prefix "Amendment QA" and note which sections were re-checked.

QA Check Categories

1. Subcontractor Validation

Check: Every sub mentioned in the Crew section exists in the project sub directory.

Finding Action
Sub name matches directory exactly Pass
Sub name is close match (fuzzy) Auto-correct and note: "Changed 'Walker' to 'Walker Construction'"
Sub name has no match Flag: "'{name}' is not in the sub directory. Is this a new sub? Add them with /process-docs or confirm the name."
Sub in directory expected on site but not listed Note: "{Sub name} is scheduled to be on site this week per the schedule but was not listed today. Were they absent?"

2. Weather vs. Work Threshold Check

Check: Compare today's reported weather against weather thresholds for the work documented.

Finding Action
Concrete work reported + temp below cold weather threshold Flag: "Concrete was placed today at {temp}. Cold weather threshold is {threshold} per {spec section}. Was a cold weather protection plan in effect? This should be documented."
Concrete work + temp above hot weather threshold Flag: "Temperature reached {temp}. Hot weather concrete protocol required per {spec section}. Document mitigation measures."
Crane operations + wind above limit Flag: "Wind reported at {speed}. Crane wind limit is {limit}. Were crane operations suspended? Document any impact."
Roofing work + rain/moisture Flag: "Roofing work documented on a day with precipitation. Confirm substrate was dry per {spec section}."
Earthwork + heavy rain Flag: "Earthwork documented with significant precipitation. Note site conditions and any impact on compaction."
No threshold conflicts Pass

3. Inspection Awareness

Check: Based on the work documented today, were required inspections noted?

Finding Action
Concrete placement documented + no pre-placement inspection mentioned Flag: "Concrete was placed today. Was a pre-placement inspection conducted? Hold point per {spec section}."
Backfill/compaction documented + no compaction test mentioned Flag: "Backfill was placed today. Compaction testing required per {spec section} every {frequency}."
Structural steel connections + no special inspection Note: "Steel connections made today. Special inspection required per IBC. Was inspector present?"
Work at hold point + inspection documented Pass
Work at witness point + no inspection Note (not flag): "Witness point for {work type}. Inspector should have been notified."

Conditional Hold Point Logic:

Some hold points are conditional — they only apply when certain thresholds are met:

  • Concrete volume > X CY may trigger additional testing requirements
  • Steel connections above certain heights may require special inspection
  • Work in specific zones (healthcare, clean room) may require additional sign-offs

When checking hold points against reported work:

  1. Load hold points for the work type from specs-quality.json
  2. If the hold point has a condition field, evaluate it against the reported work details
  3. Only flag missing inspections when the condition is met
  4. If the condition can't be evaluated (missing data), flag as INFO rather than WARNING: "Hold point may apply — verify if [condition] is met"

4. Schedule Consistency

Check: Report's schedule section aligns with known project intelligence.

Finding Action
Milestone approaching within 7 days + not mentioned Note: "{Milestone} is due in {X} days. Consider mentioning in schedule updates."
Milestone date passed + not marked complete Flag: "{Milestone} was scheduled for {date}. Is it complete? Update status."
Critical path activity mentioned with delay Flag: "This is a critical path activity. Document the delay cause, duration, and recovery plan."
Percent complete decreased from last report Flag: "Percent complete dropped from {old}% to {new}%. Is this intentional?"

5. Photo Coverage

Check: Photos are present for major work activities.

Finding Action
Concrete placement documented + no photos Note: "No photos of today's concrete pour. Consider adding photos for documentation."
Major milestone hit + no photos Note: "A milestone was achieved today. Photos are recommended for project records."
Inspection conducted + no photos Note: "Inspection documented but no photos. Photos of inspection results are recommended."
Contract requires photos + none uploaded Flag: "Contract requires {requirement}. No photos included in today's report."

6. Completeness Check

Check: All report sections have content or are intentionally blank.

Finding Action
Crew section has workers but no work described Flag: "Subs are listed but work performed is blank for {sub}."
Materials received but no condition noted Note: "Material condition defaulted to 'Good'. Confirm this is accurate."
Equipment listed as "Down" with no reason Flag: "Equipment marked as down but no reason given. Document the issue."
Delay documented with no cause Flag: "Delay noted but cause not specified. Categorize as weather/material/labor/design/inspection."
Materials marked as partial delivery with no backorder_expected date Flag: "Partial delivery of {material} noted but no expected backorder date. When is the remainder arriving?"
Materials with quantity_short > 0 but partial_delivery not marked true Note: "{material} shows a short quantity ({quantity_short}) but isn't flagged as a partial delivery. Is the remainder coming, or was the order shorted?"
Materials with quantity_received > quantity_ordered Note: "{material} received quantity ({quantity_received}) exceeds ordered quantity ({quantity_ordered}). Was extra material ordered or is this an overage?"
General Notes section empty Note: "General Notes section is empty. Anything to document? (RFIs, coordination, directives, upcoming work)"

Quantity Discrepancy Check:

When a daily report documents concrete placement, flooring installation, or any measurable work:

  1. Look up the relevant quantities in plans-spatial.json for that element/location
  2. Check the data_sources.discrepancies array for any flagged conflicts
  3. If discrepancies exist for the work being documented, add a NOTE: "Quantity discrepancy flagged for [element] — [source A] shows [value] vs [source B] shows [value]. Verify actual field measurement."
  4. If the reported quantity in the daily report differs from ALL extracted sources by >15%, flag: "Reported [quantity] for [element] differs significantly from plan quantities. Confirm measurement."

6.1 New Hold Point Detection

Check: After /process-docs adds new spec sections, verify if new hold points were added to specs-quality.json:

When running report-qa on any report following a spec update:

  • Compare current hold_points in specs-quality.json against the report-qa's cached list
  • If new hold points exist that weren't previously tracked, add a NOTE to the current report: "New hold point added from spec section [XX XX XX]: [description]. Future reports involving [work type] will be checked against this."
  • Update the cached hold points list to include the newly discovered entries

7. SWPPP Check (if applicable)

Check: If project has a SWPPP and rain was reported, was an inspection documented?

Finding Action
Rain > threshold + no SWPPP inspection noted Flag: "Rainfall of {amount} exceeds SWPPP inspection trigger of {threshold}. Was a BMP inspection conducted?"
SWPPP inspection noted + no corrective actions but issues visible Note: "SWPPP inspection conducted. Any corrective actions needed?"
No rain + no SWPPP notes Pass

8. Safety Check (if applicable)

Check: If work in safety-sensitive areas was documented, were safety measures noted?

Finding Action
Work at height + no fall protection mention Note: "Work at elevation documented in {area}. Fall protection zone per safety plan. Consider noting safety measures."
Hot work documented + no permit mention Note: "Welding/cutting documented. Hot work permit area per safety plan."
Confined space entry + no mention Flag: "Work in {location} which is a designated confined space. Permit and safety measures should be documented."

9. Delay Documentation Completeness

If delay events are documented in today's report, verify they contain sufficient detail for the delay-tracker and (if applicable) claims-documentation skills.

Finding Action
Delay logged without delay_type Flag: "Delay documented but type not specified. Classify as: Weather, Owner-Directed, Design/Spec, Material/Supply Chain, Sub Performance, Force Majeure, Permit/Regulatory, or Differing Site Conditions."
Delay logged without activities_impacted Flag: "Delay documented but affected activities not listed. Which schedule activities are impacted?"
Delay on critical path but critical_path_impact not set Flag: "This delay impacts a critical path activity per schedule.json but critical_path_impact is not flagged. Confirm critical path status."
Weather delay logged but weather section shows no adverse conditions Flag: "Weather delay documented but Weather Conditions section shows normal conditions. Reconcile — was it weather-related?"
Delay logged without estimated_duration Note: "Delay duration not estimated. Can you estimate how long this impact will last?"
Delay logged without responsible_party Note: "Delay responsibility not assigned. Who bears responsibility — owner, architect, sub, GC, or force majeure?"
Delay logged with all required fields complete Pass
No delay events documented and no delay language detected in General Notes Pass

10. Claims Mode Compliance

Only runs when claims_mode: true in project-config.json. When claims mode is inactive, skip this entire section.

Verify that claims-grade detail is captured where available. These are notes and flags, not hard requirements — the superintendent can dismiss any of them.

Finding Action
Crew entry without claims_detail.worker_names Note: "Claims mode — worker names not captured for {sub}. Consider adding for claims documentation."
Crew entry without claims_detail.start_time / end_time Note: "Claims mode — start/end times not captured for {sub}."
Equipment entry without claims_detail.equipment_id Note: "Claims mode — equipment ID not captured for {equipment}."
Equipment with status "Idle" or "Down" without claims_detail.idle_reason Note: "Claims mode — {equipment} logged as {status} but no reason documented."
Material delivery without claims_detail.delivery_ticket_number Note: "Claims mode — delivery ticket number not captured for {material} from {supplier}."
Material delivery with timing variance > 2 hours Note: "Claims mode — {material} delivery was {variance} hours late. Document impact on work activities."
Delay event without specific start/stop times Flag: "Claims mode — delay event '{description}' lacks specific start/stop times. Add timing for claims support."
Delay event without activities_impacted list Flag: "Claims mode — delay event '{description}' doesn't list affected activities. Add schedule activity references."
All claims-grade fields populated Pass: "Claims documentation complete for today's report."

Output format: Claims compliance results appear in a separate "Claims Mode" tier after the standard flags/notes/passes:

CLAIMS MODE:
• Worker names missing for Smith Electric (3 workers). Recommended for claims documentation.
• Delivery ticket not captured for rebar delivery from Harris Steel.
✓ Delay events fully documented with timing and activities
✓ Equipment IDs captured for all equipment

Project Intelligence Integration

When running QA checks, automatically cross-reference the report against the full project intelligence store. These checks supplement the category-specific checks above by catching gaps that span multiple data sources.

Punch List Cross-Check

Read punch-list.json → If the daily report documents work in a location that has open punch items (status = "open" or "in_progress"), verify the report mentions punch item status. Flag if work is documented on punch items without an update: "Work documented at {location} where PUNCH-{id} is open. Was punch item addressed? Update punch status if so."

Cost Authorization Check

Read change-order-log.json → For any new scope of work described in the report, verify it traces to an approved change order or is within original contract scope. Flag if unapproved scope work is documented: "Work on '{description}' does not match any approved CO or original contract scope. Was this authorized? If owner-directed, document the directive for CO processing."

Procurement Verification

Read procurement-log.json → If the report documents materials as "installed" or "in place," verify that procurement-log.json shows delivery_status = "delivered" for those materials. Flag mismatch: "{material} documented as installed but procurement-log shows delivery_status = '{status}'. Verify material was actually received and update procurement log."

Quality Record Correlation

Read quality-data.json → If the report mentions inspection results (pass/fail), verify that matching records exist in quality-data.json inspections. Flag if daily report mentions an inspection result not yet recorded: "Report states {inspection_type} passed at {location}, but no matching record in quality-data.json. Ensure inspection is formally logged."

Safety Incident Cross-Check

Read safety-log.json → If the report documents any safety incident, near miss, or first aid event, verify a corresponding entry exists in safety-log.json. Flag if missing: "Safety incident '{description}' documented in daily report but not found in safety-log.json. Log the incident with safety-management to maintain OSHA records."

Schedule Milestone Validation

Read schedule.jsonmilestones[] → If the report documents a milestone as "complete" or "achieved," verify that schedule.json shows the milestone status updated. Flag mismatch: "Report states '{milestone}' is complete but schedule.json still shows status = '{status}'. Update schedule to reflect completion."

Weather Threshold Verification

Read specs-quality.jsonweather_thresholds[] + daily report weather data → For each weather-sensitive work type documented in the report, cross-check the reported conditions against spec thresholds. Flag if weather-sensitive work was performed during conditions below/above thresholds and no mitigation is documented: "{work_type} performed at {temp}°F but spec threshold is {threshold}°F per {spec_reference}. No mitigation measures documented — was a protection plan in effect?"

User Response Handling

After presenting QA results:

  • If user provides corrections: Apply them to the report data, regenerate affected sections, and re-run QA on those sections only.
  • If user says "looks good" or "skip": Proceed to .docx generation with the report as-is.
  • If user addresses some flags but not others: Apply the corrections provided, note the unaddressed flags, and proceed.

Weekly Report QA Checks

When called from the /weekly-report pipeline (after section narratives are drafted but before .docx generation), run these weekly-specific checks instead of the daily checks above.

W1. Schedule Narrative vs. Actual Milestone Movement

Check: Does the schedule section accurately reflect what happened to milestones this week?

Finding Action
Milestone date changed in schedule.json version_history this week but not mentioned in schedule narrative Flag: "{Milestone} date changed from {old} to {new} on {date} but isn't mentioned in the weekly schedule section."
Narrative says "on track" but daily reports documented delays on critical path activities Flag: "Schedule narrative says 'on track' but daily reports from {dates} documented critical path delays. Reconcile."
Percent complete in weekly report differs from latest daily report by >5% Flag: "Weekly says {X}% complete but latest daily report shows {Y}%. Which is correct?"
Milestone completed this week but not called out as an accomplishment Note: "{Milestone} was completed on {date}. Consider highlighting in Executive Summary."

W2. Crew Trend Consistency

Check: Does the headcount narrative match what the daily reports actually show?

Finding Action
Weekly says "averaging X personnel" but daily report average is >15% different Flag: "Weekly states average of {X} but daily reports show average of {Y}. Verify."
Sub listed in weekly but absent from all daily reports that week Flag: "{Sub} mentioned in weekly report but not logged in any daily report this week."
Sub on site 3+ days this week but not mentioned in weekly narrative Note: "{Sub} was on site {X} days this week but isn't mentioned in the weekly narrative."
Significant headcount swing (>30% day-over-day) not explained Note: "Crew count went from {X} on {day} to {Y} on {day}. Consider noting the reason."

W3. Open Items Accuracy

Check: Do the open items in the weekly match the actual log data?

Finding Action
Weekly says X RFIs pending but rfi-log.json shows Y open Flag: "Weekly states {X} pending RFIs but log shows {Y}. Reconcile."
Weekly says X submittals pending but submittal-log.json shows Y Flag: "Weekly states {X} pending submittals but log shows {Y}. Reconcile."
RFI resolved this week but not mentioned as a closed item Note: "RFI-{XXX} was resolved on {date}. Consider noting in Open Items section."
Submittal approved this week but not mentioned Note: "SUB-{XXX} was approved on {date}. Consider noting in Materials/Open Items."
Change order status changed this week but not reflected Flag: "CO-{XXX} status changed to {status} on {date} but isn't reflected in the weekly CO summary."

W4. Weather Impact Reconciliation

Check: Does the weather summary accurately reflect daily conditions and their impact?

Finding Action
Daily reports show weather delays on X days but weekly doesn't mention weather impact Flag: "Daily reports documented weather delays on {dates} but weekly weather section shows no impact."
Weekly claims no weather delays but daily reports have weather-related notes in delays section Flag: "Weekly says no weather impact but {date} daily report noted: '{delay description}'. Reconcile."
Temperature data in weekly doesn't match daily report readings Note: "Weekly says temp range was {X}-{Y} but daily reports show {A}-{B}. Verify."

W5. Photo Coverage

Check: Are photos included and representative?

Finding Action
No photos included in the weekly report Note: "No photos selected. Weekly reports typically include 3-5 representative progress photos."
All photos are from the same day Note: "All photos are from {date}. Consider selecting from multiple days to show progression."
Major work activity documented in dailies but no photo of it in weekly Note: "{Activity} was a significant activity this week but has no photo representation."

W6. Distribution List Verification

Check: Is the distribution list current?

Finding Action
Distribution list in specs-quality.json contract.documentation_requirements is empty Note: "No distribution list configured. The user should verify who receives the weekly report."
Distribution list exists and is populated Pass

Weekly QA Output Format

Same tiered format as daily QA (Flags / Notes / Passes), but prefix the output:

Weekly Report QA Complete — X flags, Y notes

FLAGS:
• [weekly-specific flags]

NOTES:
• [weekly-specific notes]

PASSES:
✓ Schedule narrative matches milestone data
✓ Headcount averages match daily reports
✓ Open items counts match log data
✓ Weather summary matches daily conditions


Extended reference: Detailed examples, templates, scoring rubrics, and best practices are in references/skill-detail.md.

Install via CLI
npx skills add https://github.com/mgoodman60/foreman-os-plugin --skill report-qa
Repository Details
star Stars 1
call_split Forks 0
navigation Branch main
article Path SKILL.md
More from Creator