name: cost-tracking description: > Comprehensive project cost management including budget vs actual tracking, cost forecasting, variance analysis, invoice reconciliation, change order cost impact, cash flow projections, and cost reporting. Integrates with pay-app, change-order, procurement, and schedule systems. Triggers: "cost tracking", "cost report", "budget vs actual", "cost forecast", "cost variance", "invoice reconciliation", "cash flow", "budget status", "cost performance", "cost summary", "EAC", "burn rate", "cost overrun". version: 1.0.0
Cost Tracking Skill
Overview
The cost-tracking skill provides comprehensive cost management for construction projects. It enables superintendents and project managers to track actual costs against budget, forecast final costs, identify cost variances, reconcile invoices against commitments, manage change order costs, and project cash flow. The skill integrates seamlessly with pay applications, change orders, procurement logs, and schedules to maintain real-time project financial health.
Cost Tracking Philosophy
Project cost management operates on three core pillars:
- Budget Establishment — Original contract value + approved change orders = current contract value
- Cost Accumulation — Track committed costs, invoiced costs, and paid costs against each budget line
- Performance Analysis — Compare spending to schedule progress to identify cost/schedule misalignment
The cost-tracking skill manages all three pillars with early warning alerts when spending deviates from plan.
Budget Structure (CSI Division Organization)
Budgets are organized by CSI Division to align with project specifications and standard construction cost accounting:
{
"budget": {
"original_contract_value": 2770000,
"approved_cos_amount": 35000,
"current_contract_value": 2805000,
"budget_by_division": [
{
"division_number": "01",
"division_title": "General Requirements",
"description": "Site mobilization, project management, temporary facilities",
"original_amount": 145000,
"applied_cos": [
{ "co_id": "CO-001", "amount": 5000 },
{ "co_id": "CO-003", "amount": -2000 }
],
"current_amount": 148000,
"committed_costs": 65000,
"invoiced_costs": 45000,
"paid_costs": 40500,
"forecast_to_complete": 85000,
"total_forecast": 130500,
"notes": ""
},
{
"division_number": "02",
"division_title": "Existing Conditions",
"description": "Demolition and site preparation",
"original_amount": 85000,
"applied_cos": [],
"current_amount": 85000,
"committed_costs": 78500,
"invoiced_costs": 65000,
"paid_costs": 58500,
"forecast_to_complete": 12000,
"total_forecast": 77000,
"notes": ""
}
]
}
}
Budget Line Item Fields
| Field | Description | Example |
|---|---|---|
| division_number | CSI division code (01–33) | "03" (Concrete) |
| division_title | CSI division name | "Cast-in-Place Concrete" |
| description | Detailed scope summary | "Foundations, slabs, ramps" |
| original_amount | Contract baseline for this division | $185,000 |
| applied_cos | Array of approved COs affecting this division | [{"co_id":"CO-001","amount":5000}] |
| current_amount | Original + applied COs = current budget | $190,000 |
| committed_costs | PO amounts, sub contracts, approved purchase orders | $130,000 |
| invoiced_costs | Amounts invoiced by subs/suppliers (not yet paid) | $85,000 |
| paid_costs | Cumulative paid amounts | $80,000 |
| forecast_to_complete | Estimated cost to finish remaining work | $110,000 |
| total_forecast | Invoiced + forecast to complete | $195,000 |
Budget Initialization
When the superintendent first sets up cost tracking via /cost, initialize cost-data.json with:
Required fields:
original_contract_value(number) — Total contract amount from the executed contractbudget_by_division[]— Array of CSI division budget line items, each with:division(string) — CSI division code (e.g., "03", "04", "05")description(string) — Division name (e.g., "Concrete", "Masonry", "Metals")original_amount(number) — Original budget for this divisioncurrent_amount(number) — Current budget (original + approved COs)committed_costs(number) — Subcontract + PO amountsapplied_cos[](array) — Change orders applied to this division, each referencingchange-order-log.jsonentries
contingency(object):original_amount(number) — Starting contingencycurrent_amount(number) — Remaining after drawsdraws[](array) — Each draw with date, amount, description, CO reference
allowances[](array) — Contract allowances with original vs. spent tracking
Schedule of Values (SOV) linkage:
- Each division line item links to
pay-app-log.jsonSOV line items viasov_line_number - Percent complete per line feeds earned value calculations in
earned-value-management - SOV structure:
sov_line_number,description,scheduled_value,work_completed_previous,work_completed_this_period,materials_presently_stored,total_completed_and_stored,percent_complete,balance_to_finish,retainage
Cost Performance Index (CPI) Calculation
The Cost Performance Index measures how efficiently the project is spending money:
CPI = Earned Value / Actual Costs
Where:
Earned Value = Current budget × % complete
Actual Costs = Invoiced + paid costs to date
Interpretation:
- CPI = 1.0: Spending perfectly on schedule
- CPI > 1.0: Under budget (spending less than earned)
- CPI < 1.0: Over budget (spending more than earned)
Example:
- Current Budget: $2,805,000
- Project % Complete: 12%
- Earned Value: $2,805,000 × 0.12 = $336,600
- Actual Costs: $320,000 (invoiced)
- CPI = $336,600 / $320,000 = 1.05 (5% under budget)
Cost Forecasting Methods
Method 1: Estimate at Completion (EAC) — CPI-Based
Uses current cost performance to project final cost:
EAC = Actual Costs + (Remaining Work / CPI)
Or equivalently:
EAC = Budget / CPI
Example:
- Current Budget: $2,805,000
- CPI: 1.05 (spending efficiently)
- EAC = $2,805,000 / 1.05 = $2,671,429
- Projected Savings: $133,571
Method 2: EAC — Revised Estimate
Uses fresh estimate of remaining work (accounting for known scope changes):
EAC = Actual Costs + Revised Estimate to Complete
Where:
Revised Estimate = Original estimate − (% complete work)
Example:
- Actual Costs: $320,000
- Original remaining estimate: $2,485,000
- % Complete: 12%
- Revised remaining = $2,485,000 × (1 − 0.12) = $2,186,600
- EAC = $320,000 + $2,186,600 = $2,506,600
Method 3: Forecast by Burn Rate
Projects final cost based on average daily/weekly spending:
EAC = Actual Costs + (Daily Burn Rate × Days Remaining)
Example:
- Current Spent: $320,000
- Days Elapsed: 27
- Daily Burn Rate: $320,000 / 27 = $11,852/day
- Days Remaining: 124
- Forecast Remaining: $11,852 × 124 = $1,469,648
- EAC = $320,000 + $1,469,648 = $1,789,648
Variance Analysis
Variance tracking identifies where costs deviate from plan:
Budget Variance by Division
Budget Variance = Current Budget − Total Forecast
Or as % of Budget:
Variance % = (Budget Variance / Current Budget) × 100%
Example — Division 03 (Concrete):
- Current Budget: $190,000
- Total Forecast (invoiced + remaining): $195,000
- Variance: −$5,000 (5.3% over budget)
- Flag: Red alert when variance exceeds ±5%
Schedule Variance Impact on Costs
When a project falls behind schedule, labor and overhead costs extend:
Schedule Variance Cost = Daily overhead rate × Days behind schedule
Where:
Daily overhead = (Division 01 budget / Total project days)
Example:
- General Requirements (overhead): $145,000
- Total project days: 151
- Daily overhead: $145,000 / 151 = $961/day
- If 10 days behind schedule:
- Schedule Variance Cost = $961 × 10 = $9,610
Material Cost Variance
Actual material costs vs. estimated:
Material Variance = (Actual Material Cost − Budgeted Material Cost)
By Line Item:
Concrete variance = Actual spent on concrete − budgeted for concrete
Steel variance = Actual spent on steel − budgeted for steel
Example:
- Budgeted PEMB Steel (Division 05): $85,000
- Committed through supplier POs: $88,500
- Material Variance: −$3,500 (4.1% over)
Contingency Tracking
Contingency is reserve funds to cover unforeseen conditions and changes:
{
"contingency": {
"original_contingency_amount": 150000,
"contingency_percentage_of_budget": 5.4,
"spent_against_contingency": [
{ "co_id": "CO-001", "amount": 50000, "description": "Owner-directed scope addition" },
{ "co_id": "CO-003", "amount": -15000, "description": "Value engineering credit" }
],
"total_spent_from_contingency": 35000,
"available_contingency": 115000,
"available_contingency_percentage": 4.1,
"drawdown_rate_per_month": 5833,
"months_of_contingency_remaining": 19.7,
"alert_threshold_percent": 50,
"contingency_status": "healthy"
}
}
Contingency Drawdown Rules:
- 0–25% drawn: Green — Healthy reserve
- 25–50% drawn: Yellow — Monitor closely
- 50–75% drawn: Orange — Review budget; may need change order to owner
- 75%+ drawn: Red — Contingency at risk
Invoice Reconciliation Process
Sub Invoice Verification Workflow
- Receive Sub Invoice: Sub submits invoice for work/materials
- Verify Against SOV: Check invoice amount ≤ (% complete × contract amount)
- Cross-Reference with Pay App: Confirm line items match SOV
- Flag Overbilling: If invoice > % complete, reject or request clarification
- Apply Retainage: Hold back 10% (or contract rate) from payment
- Process Payment: Pay sub after conditional lien waiver received
- Update Cost Tracking: Record payment in cost-data.json
Overbilling Detection
Maximum billable amount = Line item contract amount × % complete
Example:
Division 03 contract: $185,000
Division 03 % complete: 45%
Maximum billable: $185,000 × 0.45 = $83,250
If invoice shows: $87,000 → FLAG OVERBILLING
Difference: $3,750 excess
Action: Request clarification or deny until work verified
Retainage Tracking by Sub
{
"sub_retainage_tracking": {
"subcontractor": "W Principles (Concrete)",
"contract_amount": 185000,
"invoiced_to_date": 120000,
"retainage_rate": 0.10,
"retainage_held": 12000,
"amount_paid": 108000,
"percent_complete": 65,
"retainage_policy": "W Principles flat 10% until substantial completion",
"retainage_released_at_substantial_completion": true,
"notes": "Flat 10% retainage per W Principles standard"
}
}
Project Intelligence Integration
When project intelligence is loaded, cross-reference cost data against extracted quantities, schedule progress, and procurement to identify cost risks early.
Quantity Verification
Compare budgeted quantities against plan-extracted quantities:
- Read
plans-spatial.json→quantities→ for each CSI division, sum the relevant quantities (concrete CY, wall SF, flooring SF, fixture counts, etc.) - Compare against budget line items in
cost-data.json→budget_by_division[] - Calculate: Plan quantity × estimated unit rate vs budget amount
- Flag divisions where plan quantities exceed budget quantities by >5% — this indicates the estimate may have missed scope
- Example: Division 03 budget assumes 38 CY total concrete, but plans-spatial.json quantities show 42.3 CY → flag 11% overage for review
Schedule-Cost Alignment
Cross-check cost progress against schedule progress:
- Read
schedule.json→percent_complete→ overall project progress - Compare with cost % complete per division: (invoiced_costs / current_amount) for each budget line
- Flag front-loading: If cost % complete significantly exceeds schedule % complete for a division, the sub may be overbilling
- Flag lagging: If cost % complete is far below schedule % complete, work may be unbilled or behind
- Example: Schedule 25% complete, Division 03 (Concrete) 40% billed → possible front-loading
Change Order Linkage
Verify change order cost impacts are properly reflected in budget:
- Read
change-order-log.json→ for each CO with status "approved" - Check that the CO's
cost_approvedamount appears in the correct budget division'sapplied_cos[]array - Flag any approved COs not yet reflected in budget divisions
- Example: CO-005 approved for $17,800 affecting Division 26 → verify Division 26
applied_cosincludes CO-005
Procurement Cost Tracking
Compare committed material costs against budget line items:
- Read
procurement-log.json→ sumtotal_costby spec section → map to CSI divisions - Compare against budget division
committed_costs - Flag material cost overruns before they hit invoicing
- Example: Procurement for Division 05 (Steel) totals $88,500 committed, but budget shows $85,000 → flag $3,500 (4.1%) material cost overrun
Extended reference: Detailed examples, templates, scoring rubrics, and best practices are in